Kick-off: April 1, 2026Digital Experience
Digital Experience
Integration Project
Hybrid approach combining delivery velocity with governance rigor. 48-week execution with formal Steering Committee oversight, PMO governance, and enhanced compliance frameworks. Integrates 8 digital channels with Medallia and Sprinklr for comprehensive customer experience management.
Total Budget
$350-375kHybrid Approach
Governance + Compliance Enhanced
Duration
48 Weeks
Apr 1, 2026 - Feb 15, 2027
Team Structure
12 Roles
9 Consultant + 3 Authority
Integrations
8 Channels
Medallia Hub
Project Phases
Current progress and upcoming milestones
1. Planning (Weeks 1-4)Ready to Start
2. Foundation (Weeks 5-10)Pending
3. Configuration (Weeks 11-18)Pending
4. Preparation (Weeks 19-24)Pending
Project Highlights
Lean Model Optimized
Budget reduced by ~65% from initial estimate
Hybrid Delivery
51% On-site / 49% Remote mix
No WSO2 Required
Direct API integration strategy selected

Expert Team
A core team of 3-4 senior experts supported by on-demand specialists ensures efficiency and quality.