Financial Overview
Hybrid approach budget analysis with enhanced governance, compliance frameworks, and knowledge transfer. 48-week execution timeline with formal governance structure.


Rate Strategy
The project utilizes a competitive rate structure of $75/hr for On-Site and $47/hr for Remote resources. This strategic pricing allows for high-quality delivery while maintaining budget compliance.
Recommendation: Monitor project scope and resource utilization closely. Contingency fund is fully available for risk mitigation or scope adjustments.
- Planned Spending
Peak Spending: June 2026 ($62k) during Configuration phase. Spending tapers off in Q4 2026 and Q1 2027 during stabilization.
- Cumulative Spending
Projection: Total baseline spending of $273,596 will be distributed across 10 months, with project completion by February 15, 2027.
Total Project Budget
$313,859
Project Duration
46 Weeks
On-Site Work
$196,950
2,627 hours @ $75/hr
Remote Work
$66,646
1,418 hours @ $47/hr
Contingency (12.8%)
$40,263
Risk mitigation buffer
| Milestone | Percentage | Amount | Status |
|---|---|---|---|
| P1: Contract Signing | 10% | $31,386 | Pending |
| P2: Planning Complete | 10% | $31,386 | Pending |
| P3: Foundation Complete | 15% | $47,079 | Pending |
| P4: Configuration Complete | 20% | $62,772 | Pending |
| P5: Preparation Complete | 15% | $47,079 | Pending |
| P6: Testing Complete | 10% | $31,386 | Pending |
| P7: Training Complete | 5% | $15,693 | Pending |
| P8: Launch Complete | 10% | $31,386 | Pending |
| P9: Project Closure | 5% | $19,112 | Pending |
| TOTAL | 100% | $294,660 |